The project
Overview
Analytical calculations and Computer modeling was conducted to refine the dewatering system design, in order to come up with an optimised cost effective solution.
ACTION designed a dewatering system for sufficient deep wells around the area of the excavation to achieve the desired drawdown.
5.3M
Maximum system flow rate
180,000 m3 /day
Operation per day
~45 Days
Operating duration
The requirement
Project challenge
Cost effective solutions, Monitoring team, Dry platform for the main contractor to work in at all times
24/7 continuity of dewatering works and to ensure the safety of the contractor’s equipment and staff working within the excavation
The response
ACTION solution
On site