Palm Jumeirah Vehicular Tunnel Project
The project
Overview
ACTION dewatered 5.3 million cubic meters of seawater trapped within the cofferdam in only 45 days in preparation for construction.
ACTION engineered a temporary variable-speed pumping solution with a maximum pumping capacity of 180,000 m3 /day to ensure works were carried out within the tight project schedule.
5.3M
Maximum system flow rate
180,000 m3 /day
Operation per day
~45 Days
Operating duration
The requirement
Project challenge
Design, supply, installation, commissioning, and maintenance, pipeline installation
24/7 continuity of dewatering works and to ensure the safety of the contractor’s equipment and staff working within the excavation
The response
ACTION solution
On site