Overview
Seawater flushing, pressure testing and chemical cleaning of a 48-inch subsea pipeline.
ACTION designed and installed the pumping, filtration, power and water-storage system for the Fujairah project.
1,000 m³/h
Maximum system flow rate
24 hours
Operation per day
~2 weeks
Operating duration
The requirement
Project challenge
Connecting the sea intake to the pipeline.
The system needed to supply seawater to a suction point approximately one kilometre from the sea, supporting the required flow rate and chemical dosing during continuous operation.
The response
ACTION solution
On site